| WORLD WIDE RE-INJECTION PROJECTS |
 |
| CUTTING RE-INJECTION (CRI) BASIC FLOW DIAGRAM |
|
DCDC CRI UNIT |
|
FOUNDERS OF DCDC EXPERIENCE
First to inject successfully in many countries
Usually only one injection point, if failed, finished
Have always found a subsurface strata we could dispose waste successfully and did so
Took over/Fixed other’s CRI Unit/project
In many country projects with no previous wells drilled, used seizmic data to design disposal project
Have had over 40 CRI projects ongoing around the world, at one time, while planning others
|
CRI OPERATIONS |
| OPERATOR |
LOCATION |
INJECTION INFORMATION |
BBLS. INJ. |
WELLHEAD SYSTEM |
HOLE SIZE |
DRILL RATE |
# OF WELLS |
| British Gas |
Offshore Tunisia |
Imperable Claystone |
162,476 |
Mud Line Suspension, SubseaTemplate |
12 1/4 |
400 FPH |
13 |
| Hunt Oil |
West Texas Land |
Chalk |
178,426 |
tbg/perf |
Pit |
3000 B/d |
n/a |
| Amerada Hess |
North Dakota, Land |
Tight Sandstone |
48,452 |
tbg/perf |
Pit |
2700 B/d |
1 |
| Hunt Oil |
South Louisiana, Land |
Loose Sandstone |
675,000 |
tbg/perf |
Pit |
3500 B/d |
10 |
| Numerous Opererators (1,7) |
Gulf of Mexico |
Sand/Shale Intervals |
1,200,000 |
tbg/perf/annular, MLS, depleted zones |
12 1/4 |
280 FPH |
18 |
| Numberous Operators |
Gulf of Mexico |
Sand/Shale Intervals |
2,300,000+ |
Annular |
12/1/2004 |
300 FPH |
85 |
| Shell U.K. (6) |
Brent Bravo North Sea |
Clay/Sandstone |
132,476 |
Annular |
12 1/4 |
200 FPH |
7 |
| BP U.K. (5,7) |
BP Andrew North Sea |
Sand/Shale |
137,476 |
tbg/perf/annular |
16 |
250 FPH |
9 |
| BP Venezuela (7) |
Barge Clean Out |
Claystone/Geologic Upthrust |
56,000 |
Annular |
16 |
1500 B/d |
n/a |
| Phillips Alaska (4,7) |
Cook Inlet Alaska |
Sand/Coal/Shale |
48,279 |
Injection String |
12 1/4 |
150 FPH |
4 |
| Unocal/Spirit Energy (7,1) |
Gulf of Mexico (offshore) |
Sand/Shale |
12,724 |
Annular |
12 1/4 |
1 Mile/24 Hrs. |
10 |
| Enron India (7) |
Offshore India |
Imperable Claystone |
32,472 |
tbg/perf/annular |
12 1/4 |
400 FPH |
6 |
| Pan Canadian/Nova Scotia (7,2,1) |
North Atlantic |
Imperable Shale/Clay |
24,274 |
tbg/perf |
12 1/4 |
200 FPH |
3 |
| Conoco (7,1) |
Gulf of Mexico |
Sand/Shale |
18,275 |
Mud Line Suspension |
6 1/2 |
Rig Trash |
1 |
| Unocal/Thailand (7) |
Gulf of Thailand |
Tight Sandstone |
4,671 |
depleted zone tbg/perf |
n/a |
Hg Prod Slud |
1 |
| Numerous Opererators |
Gulf of Mexico |
Depleted Sandstone |
74,387 |
tbg/perf |
n/a |
NORM/LSA |
16 |
| BP Wytah Farm (3,7) |
South of England, Land |
Sand |
12,476 |
3000 ft Horizontal tbg/perf |
17 1/2 |
200 FPH |
2 |
| Shell Sakhalin |
Offshore Sakhalin |
Sand |
187,354 |
Disposal Well/Annular |
17 1/2 |
200 FPH |
6 |
| Exxon Sakhalin |
Offshore Sakhalin |
Fine, Soft Sand/Clay Mix |
14,723 |
Annular |
12 1/4 |
200FPH |
1 |
| 1-
Vacuum Assist 2- Montoring Pkg, Fully automated, single
lift Pkg 3- Comingle Production and Slurry 4- tbg injection
allowed injection of drill cuttings immediately after drilling out from
undre surface 5- North Sea record of 2200 Barrels of
cutting slum processed and injected 6- Best Mechanical
Engineering Award 1997- OTC 7- Ongoing |
|
SHELL - NORTH SEA BRENT CRI UNIT

|
CRI DESIGNED FORMAT
Regulatory regime, top side, environment and subsurface
Type of Rig or Platform, place equipment, utilities, inj. Line setup for zero discharge and collection of waste’s
Annular, tbg/depleted zone, disposal well
Subsurface Disposal Strata
Disposal point Verses production or fresh water zone,fracture’s or faulting and well’s to be drilled
Hole Size/Drill Rate/Volume to be injected
Required Safe Injection Pressure
Casing/Cement Design/path
Topside design
Installation/, Operations Plan and Contingencies
|
CRI DESIGNED FORMAT
 |
Install, Commission, Initiate Injection Test, Compare to Expected Formation Reaction, Adjust if necessary
Ongoing Monitoring/Adjustment/ and Slurry Placement Assurance
Monthly/End of Well Reports and Follow Up
Suspend or Plug Injection Conduit, End Report
|
Survey Rig, Design Surface Equipment/Interface Prepare Detail
Procedures Manual including pumping program, displacements, pressure
profiles, ISIP’s, Drawdown’s, Contingencies, Initial Injection Test
Procedures, Slurry Rheology/Particle Size Requirements, Preventative
Maintenance, Monitoring Reports, Chain of Command, Permit, Well
Construction, Feasibility Study, Contingencies, etc. Personnel
Selection/Training/Support Regulatory Permits, Logistics/Customs
Requirements |
Research all Offset Well Data, Seismic Data, Wells, Faults, Production,
Fractures in area of injection, geology of area Review Regulatory
Regime and Operator Requirements Review Future well drilling plans
Prepare inputs for Proprietary Fracture Model, Test different Injection
Zones, Determine best practices approach, make recommendations Outputs
are used to design disposal well, and/or review future and existing
well construction, cementing, develop procedures |
Experienced,
Focused Management review all data, run Models, and are involved in
preparing the operations procedures manual, disposal design, Rig
Survey, surface equipment design/interface, Personnel Selection and
Training, therefore, are completely familiar and Client has One party
Responsibility, Our Program has worked since 1987! |
|
OUR FRACTURE MODELING IS DONE BY AN EXPERIENCED CRI OPERATIONS MANAGER, WHO IS WORKING ON YOUR PROJECT TEAM |
|
DISPOSAL REGIME INPUT DATA |
|
Formation Lithology
Mechanical and chemical properties
Fracture Gradient Profile
Pore Pressure Curve
Anticipated Csg. /Csg. Cement Design
Existing Wells/Csg./Cement Design in the area of planned CRI
Geology of the area
Formation/Resistivity logs
|
DISPOSAL REGIME OUTPUT DATA |
|
Cuttings Injection Rates/Pressures
Disposal Profile
Slurry Particle Size/Rheology
Disposal Formation
Confining Formation/cmt. required
|
|
TYPICAL SLURRY PROPERTIES
|
|
PARTICLE SIZE ANALYSIS |
|
FRACTURE PROFILES
|
|
VERTICAL WIDTH PROFILES
|
|
ANNULAR INJECTION PROFILE
|
|
SOME RE-INJECTION OPTIONS
|
|
BRENT BRAVO SUMMARY
< <
| BB-32-S3 |
Total barrels of slurry re-injected |
|
= 10,919 |
Documented cost to run C.R.I. |
|
= 64,559.64 |
Total cost per barrel of slurry re-injected |
|
= 5.91 |
| |
|
|
|
| BB-14-S1 |
Total barrels of slurry re-injected |
|
= 9,155 |
| |
Documented cost to run C.R.I. |
= 101,729.64 |
|
| |
Total cost per barrel of slurry re-injected |
|
= 11.11 |
| |
|
|
|
| BB-19-S2 |
Total barrels of slurry re-injected |
|
= 4,414 |
| |
Documented cost to run C.R.I. |
= 78,469.66 |
|
| |
Total cost per barrel of slurry re-injected |
|
= 17.78 |
| |
|
|
|
| BB-01-S1 |
Total barrels of slurry re-injected |
|
= 12,773 |
| |
Documented cost to run C.R.I. |
= 53,528.48 |
|
| |
Total cost per barrel of slurry re-injected |
|
= 4.19 |
| |
|
|
|
| BB-01-S2 |
Total barrels of slurry re-injected |
|
= 7,267 |
| |
Documented cost to run C.R.I. |
= 45,833.86 |
|
| |
Total cost per barrel of slurry re-injected |
|
= 6.31 |
| |
|
|
|
| BB-01-S3 |
Total barrels of slurry re-injected |
|
= 9,034 |
| |
Documented cost to run C.R.I. |
= 94,131.72 |
|
| |
Total cost per barrel of slurry re-injected |
|
= 10.42 |
| |
|
|
|
| |
The average cost per barrel (Over 6 Wells) |
= 8.18 |
|
| |
The average cost per tonne (Over 6 Wells) |
|
= 42.87 |
INJECTION PRESSURE AND CUMULATIVE VOLUME COMPARATIVE GRAPH
|
|
 |
|